Director of Enguri HPP - The 500-kilowatt line of Imereti was turned off - a very large load was passing through, when it was turned off, the regime was violated and the entire energy system collapsed

The Director of Enguri HPP, Levan Mebonia, states that the large-scale power outage was caused by the shutdown of the 500-kilowatt line of Imereti.

According to him, the regime was violated and the energy system collapsed.

“The 500-kilowatt line of Imereti was turned off. ... The line was turned off, the line is not at my disposal, we are connecting the units.

The main load - Enguri is connected to the energy system up to Zestaponi. A very large load was passing through - when it was turned off, the regime was violated and the entire energy system collapsed. We are in the process of eliminating the problem,” he noted in a telephone comment to TV Pirveli.

According to the Georgian State Electrosystem, electricity supply was fully restored throughout the country by 10:15 a.m. The emergency power outage occurred at approximately 8 a.m. The cause of the outage is currently being determined, according to the State Electrosystem. A similar incident occurred on July 24, when power was cut off across Georgia.